CONSTRUCTION SCHEDULE

Construction for Harbor Avenue Campus began in early June.

July 2017: Demolition

August 2017 - October 2017: Earthwork & Utilities

October 2017 - February 2018: Underground & Foundation Work

February 2018 - July 2018: Concrete

Please stay tuned for further details.

ESTIMATED MILESTONES

July 2018 - December 2018: Exterior & Interior Finishes

January 2019 - February 2019: Interior Finishes

Spring 2019 - Tenant Improvements

UPDATES

There are no updates at this time.